County Commission Approves Change Order for Livestock & Expo Center Concrete Work

County Commission Approves Change Order for Livestock & Expo Center Concrete Work

During their February 20, 2024 meeting, the County Commission addressed a concern in changing concrete work at the Livestock & Expo Center. Initially awarded to Smoky Hill Construction for $174,000 on August 8th, 2023, the project aimed to upgrade the animal wash station and improve drainage between Barns 5 & 6 to mitigate erosion.

However, following the installation of drainage structures, a significant gap between the barns and the structures was identified, necessitating additional measures to prevent dirt washout. The proposed change order involves the installation of concrete curb-like structures on each side of the drainage to address this issue, requiring approximately 300 linear feet of concrete at an additional cost not exceeding $13,200.

After deliberation, the Commission approved the change order, as recommended by Hutton and Smoky Hill Construction. The added expense will be drawn from the Livestock & Expo Center's 2024 Capital Improvement Program budget of $218,947.

Great! Next, complete checkout for full access to Salina311.
Welcome back! You've successfully signed in.
You've successfully subscribed to Salina311.
Success! Your account is fully activated, you now have access to all content.
Success! Your billing info has been updated.
Your billing was not updated.