Progress Report: Lee Mercantile Lofts (Phase 2) Construction Update
Behind the façade of Lee Mercantile Lofts, Phase 2, a flurry of activity unfolds as historic preservation meets modern renovation. A symphony of coordination among consultants, architects, engineers, and regulatory bodies ensures that every aspect of this restoration is meticulously executed.
Here's the latest:
- Mechanical Contractor: The basement duct work and unit installation are underway.
- Electrical Contractor: Progress continues on the 4th and 5th floors with overhead conduit installations.
- Plumbing Contractor: Work progresses on the 3rd floor with in-wall plumbing rough-ins and preparations for shower installations on the 5th floor.
- Fire Suppression Contractor: Installation of piping on the 3rd floor is ongoing.
- Masonry Contractor: Restoration work on the exterior brick along the West and East elevations is in full swing, alongside the creation of openings on the 1st floor.
- Framing Contractor: From drywall top-outs on the 5th floor to insulation on the 4th floor and resilient channel installations on the 3rd floor.
- Coring Contractor: Preparation for new windows on floors 4 and 5 involves precise cutting through exterior walls.
- Upcoming Milestones: Assembly and hoisting of mechanical roof supports, and the commencement of site grading for the courtyard.
Lee Mercantile Lofts Phase 2 stands as a testament to the intricate dance of preserving history while embracing modernity. Stay tuned for more updates as this landmark development continues to take shape.