On Wednesday, April 19, Smoky Hill, LLC of Salina closed to traffic the intersection of Lincoln and Reynolds to repair leaking storm sewer pipes.
Barricades at the nearest intersections inform motorists that the road is closed to through traffic. Access to all properties will be maintained.
Weather permitting, the work will be complete in four weeks.
The $153,000 project, which also includes drainage improvements at the intersection of 9th and Iron, was a part of the City of Salina's $4.7 million 2022 street maintenance capital improvement program.