Lee Mercantile Lofts (Phase 2) Progress Report as of December 18, 2023
As construction at Lee Mercantile Lofts (Phase 2) advances, significant developments mark the latest update as of December 18, 2023:
- Historic Storefront Unveiling:
The removal of glass blocks, installed years ago to preserve historic window openings, has revealed the captivating historic storefront entries. - MEP Collaboration and Unit Framing:
MEP contractors are actively collaborating on the floor layout, contributing to the ongoing framing construction of residential units. - Electrical Progress:
The electrical contractor has initiated roughing in on the east 5th floor and successfully completed electrical pathways in the basement. - Plumbing Layout:
The plumbing contractor is diligently laying out 2nd-floor penetrations, ensuring precision in the construction process. - Masonry Restoration:
The masonry contractor is engaged in large-scale brick tuck-pointing, addressing both exterior and interior repairs above windows. - Demolition Milestones:
The demolition contractor has achieved significant milestones by completing the east elevator demolition and addressing the remaining roof chimney. - Flooring Milestones:
The lightweight concrete contractor has made substantial progress by successfully pouring concrete on floors 5, 4, 3, and 2, with ongoing work on the 1st floor. - Fire Suppression System Verification:
The fire suppression sprinkler system contractor is conducting field verification to ensure precise dimensions before commencing work.
The Lee Mercantile Lofts (Phase 2) project is on track, with each specialized contractor contributing to the transformation of this historic space. Stay tuned for further updates as this iconic development continues to take shape.