This week at Lee Mercantile Lofts, significant strides have been made in the ongoing construction efforts. Here are the key developments and visual highlights:
Roofing Renovation: The roofing contractor has embarked on the meticulous task of removing the existing roofing materials from the roof and replacing the decking. The west roof is nearly completed. Meanwhile, work on the east roof is in progress, with both decking and roofing material replacement underway.
Elevator, Roof, and Basement Fixtures: The demolition contractor has commenced the demolition of the elevator, as well as the removal of the roof and basement fixtures.
Masonry: The masonry contractor has set up hydraulic scaffolding to initiate the process of raking out existing mortar joints. This is a step towards the meticulous tuck pointing and brick replacement.
Plumbing: The plumbing contractor is making headway by excavating and benching an opening for the waterline entry into the building through the basement wall.